Compute
the NPV for the following project. The initial cost is $5,000. The net
cash flows are $1,900 for four years. The net salvage value is $1,000
when the project terminates. The cost of capital is 10%.
a. $1,705.76
b. $5,000.00
c. $6,705.76
d. none of these
a. $1,705.76
b. $5,000.00
c. $6,705.76
d. none of these