Goldratt’s rule of production scheduling include all but:
a. Do not balance the capacity – balance the flow
b. Utilization and activation of a resource is not the same thing
c. An hour saved at a non-bottleneck is a mirage
d. A process batch should be fixed both along its route and in time
e. Priorities can be set only by examining the system’s constraints
a. Do not balance the capacity – balance the flow
b. Utilization and activation of a resource is not the same thing
c. An hour saved at a non-bottleneck is a mirage
d. A process batch should be fixed both along its route and in time
e. Priorities can be set only by examining the system’s constraints