Which of the following most closely describes net material requirements?
a. gross requirements – planned order receipts
b. gross requirements – on-hand + planned order receipts
c. gross requirements – on-hand – planned order receipts
d. gross requirements – planned order releases
e. none of the above
a. gross requirements – planned order receipts
b. gross requirements – on-hand + planned order receipts
c. gross requirements – on-hand – planned order receipts
d. gross requirements – planned order releases
e. none of the above