Which of the following would not be considered in deciding how far to minimum-cost schedule (crash) a project?
A. Project overrun penalties
B. Incentives for early completion
C. Indirect project costs (e.g. interest on a construction loan)
D. The normal duration times of tasks not on a critical path
A. Project overrun penalties
B. Incentives for early completion
C. Indirect project costs (e.g. interest on a construction loan)
D. The normal duration times of tasks not on a critical path