Sunday, 17 June 2012

Which of the following would not be considered in deciding how far to

Which of the following would not be considered in deciding how far to minimum-cost schedule (crash) a project?
a. Project overrun penalties
b. Incentives for early completion
c. Indirect project costs (e.g. interest on a construction loan)
d. The normal duration times of tasks not on a critical path
e. How far individual tasks can be crashed
 

No comments:

Post a Comment

Note: only a member of this blog may post a comment.