Which statement is true about Project Scheduling?

Which statement is true about Project Scheduling?
a. Slack is defined as the difference between the earliest start and the latest finish of a task.
b. The critical path seldom has a slack time of zero.
c. Project crashing is an effort to maximize project duration.
d. The earliest finish for a task is equal to the early start plus the task duration.
e. None of the above statements are true.
 